The Chilkat Valley News, Haines Alaska
Chilkat Valley News, Haines, Alaska Serving Haines and Klukwan since 1966
Chilkat Valley News, Haines Alaska

Volume XXXVIII    Number 45,  Nov.  27, 2008

Front Page

Duly Noted

Letters

Unclassifieds

News Archive


About CVN

Contact Us

Subscribe

Advertise



Lutak repave delayed
as contractor defaults

By Tom Morphet

Southeast Roadbuilders of Haines has defaulted on a $12 million bid to widen and repave Lutak Road from the ferry terminal to town, delaying the project the state Department of Transportation planned to begin this summer.

The two-year job was expected to provide a direct boost to the Haines economy. Southeast Roadbuilders uses local operators and it projected a payroll of more than $5 million for the work.

In mid-May, the local firm bid $11.5 million on the job the state estimated would cost $12.7 million, apparently topping bids from two other firms, Secon of Juneau ($15.4 million) and Kiewit Building Group, Inc. of Anchorage ($18.3 million).

According to Mal Menzies, director of DOT in Southeast, company president Roger Schnabel immediately was worried about the bid, asking if he could review his numbers and talking with state construction engineers.

When the company was scheduled to post a performance bond for the job, Schnabel instead told the state he had made an administrative error in the bid and would like to withdraw it.

State engineers are now reviewing Schnabel’s claim that the mistake was an administrative error (such as a missed decimal point) and not an error in judgment (such as an estimation of being able to do the job faster or better than a competitor), Menzies said.

"Roger realizes the seriousness of this and he has submitted preliminary evidence of an administrative error. We said those documents weren’t complete and asked for more information," Menzies said.

The difference between the two kinds of mistakes is significant. The state can forgive an administrative error but if it determines the mistake was one in judgment, Schnabel would have to forfeit a $550,000 bond to withdraw from the work, possibly damaging his ability to secure future bonding from insurers.

"This is a big decision for us," said Menzies. ""It’s all about him proving to us he did make an administrative error… This has happened in the region in the past, but not with numbers this big."

Schnabel said this week the error stemmed from a traffic control problem, based on interpretation of contract documents.

DOT’s decision on the question must be approved by an attorney general. Menzies said he expected it by Friday. Even if it’s favorable to Schnabel, Menzies said he expects the job would go to the second-lowest bidder.

"We don’t want to rebid the project. The project has been lingering for the community of Haines for too long. We want to go forward as fast as we can," Menzies said.

But the job might be rebid if Schnabel were to protest awarding the job to the second-highest bidder on grounds that there was a mistake in the state’s plans or engineering for the job. "Roger hasn’t said that yet, but it’s still a strong possibility," Menzies said.

Schnabel told the CVN this week he was not at this time planning on filing such a protest.

Re-bidding would delay the two-year job as much as a year, and it’s not clear whether Schnabel would be eligible to submit a bid, Menzies said. "We’ve asked the attorney general on a ruling for that. Common sense tells you you can, but it would be really weird."

The bids by Southeast Roadbuilders and Secon were in the typical range for such a job, Menzies said. Schnabel was 10 percent below the state engineer’s estimate for the work and Secon was 15 percent above. "Roger was not that far off. Usually you have to be 20 to 25 percent above or below the engineer’s estimate to raise the engineer’s eyebrow."

Menzies said Southeast Roadbuilders has done more difficult jobs than improving the four-mile stretch between the Haines ferry terminal and town, including construction of three miles of remote road for a power station along Taku Inlet that came off "with flying colors."

"His ability is among the best in Southeast… I think the biggest surprise was Roger’s."

Secon and Kiewit are owned by international firms. Southeast Roadbuilders outbid Kiewit for a section of the Haines Highway widening project between 34 Mile and 42 Mile in 2000. The local firm completed a $17 million project on Prince of Wales Island last year.

 

 

 

 
 


Sponsored link:

      Advertise your weblink here


Links:

      Hainesak.com
     Haines Visitor Center
     Haines Chamber of Commerce







Chilkat Valley News
Main Street - PO Box 630
Haines AK 99827
(907) 766-2688
cvn@chilkatvalleynews.com

This site copyright (c) 2008
   Chilkat Valley News

Last modified: Saturday, 21-Jun-2008 07:24:14 PDT